IELTS Reading
Academic Reading — Test 127
3 passages · 40 questions, in the real IELTS Reading format. Read each passage, answer its questions, then submit once for your score.
IELTS — TestDayTwin Practice
Question 1 of 4060 minutes remaining
Reading passage
When the Sydney Harbour Bridge opened to traffic in March 1932, it represented one of the most ambitious engineering projects ever attempted in the southern hemisphere. The challenge that had faced its designers was formidable: the waterway it was intended to cross was both wide and deep, and it carried heavy shipping traffic that could not be interrupted for years on end. A conventional bridge resting on a forest of piers driven into the harbour bed was therefore impractical, since such piers would have obstructed vessels and proved enormously expensive to sink in such deep water. The solution adopted was a single great steel arch, and the method chosen to erect that arch relied on a clever application of the cantilever principle.
A cantilever is, in essence, a beam or structure that is supported at one end only, projecting outward into space while remaining firmly anchored behind. The genius of cantilever construction lies in the fact that it allows builders to extend a structure across a gap without any temporary support rising from below. In the case of the Sydney Harbour Bridge, the two halves of the arch were built outwards simultaneously from opposite shores, each half growing steadily towards the centre of the harbour. Until the two arms finally met in the middle, each was effectively a gigantic cantilever, held back by an elaborate system of restraint rather than propped up from beneath. This approach left the shipping lanes completely clear throughout the years of construction, which was a decisive advantage.
The forces involved were enormous, and preventing the half-arches from toppling forward into the water demanded ingenious anchoring. Engineers excavated tunnels into the sandstone on each side of the harbour and installed massive steel cables that ran from the rear of each half-arch back into these tunnels. The cables, numbering many strands, acted as restraints, holding the growing arms securely in position as they crept outwards. As each new section of steelwork was added at the front, the tension in the cables was carefully adjusted to keep the structure balanced. This delicate management of forces was central to the whole undertaking; an error in the calculations could have proved catastrophic. The work was supervised by the firm responsible for the design, and the steel itself was largely fabricated on site at a specially built workshop.
The actual assembly of the steelwork was carried out by creeper cranes, which were mounted on the arch and travelled along it as construction advanced. Each crane lifted the heavy steel members into place, where teams of riveters then secured them. Riveting was hot, dangerous and physically demanding labour. A rivet was heated until it glowed, thrown to a worker who caught it, and then hammered into a hole while still soft so that it would contract and grip tightly as it cooled. Millions of rivets were driven during the project, and the men who performed this work laboured at great heights above the harbour, frequently in exposed and perilous conditions. Several workers lost their lives during construction, a sober reminder of the human cost behind the structure.
The most anxiously awaited moment of the entire programme came when the two cantilevered halves were brought together. As the arms approached one another high above the water, the engineers gradually slackened the restraining cables, allowing the two halves to lower and lean towards each other until their ends finally met. This closing of the arch was a tense and precise operation, dependent on accurate measurement and favourable weather, since the steel expanded and contracted noticeably with changes in temperature. Once the arch was joined into a single continuous span, it became self-supporting, and the cables that had restrained the cantilevers were no longer needed for that purpose. The deck carrying the roadway and railway tracks was then suspended from the arch by vertical hangers, and the bridge gradually took on its familiar finished form.
The completed structure stands as a landmark not only of the city it serves but of structural engineering more broadly. By exploiting the cantilever method, its builders managed to throw a single graceful arch across a busy harbour without ever blocking the water beneath. The principles they applied were not in themselves new, for cantilever bridges had been built elsewhere before, yet the scale at which they were deployed in Sydney was remarkable for its time. Decades later, the bridge remains in daily use, a testament to the soundness of the engineering and the courage of those who built it.
1.
True / False / Not Given
Do the following statements agree with the information in the passage? Choose True, False, or Not Given.